How to start the 2be water ring vacuum pump correctly
How to start the
2be water ring vacuum pump correctly? It needs to be started in a certain order
to ensure the normal and stable operation of the equipment, while improving the
working efficiency. Here is a detailed introduction:
1. It is preferred
to close the high vacuum butterfly valve on the intake pipe.
2. Start
the 2be water ring vacuum pump motor.
3. Open the gate valve on the
water supply pipeline, the water supply will gradually increase until the water
supply meets the requirements.
4. When the pump reaches the limit
vacuum, open the gate valve on the intake pipe, and the 2be water ring vacuum
pump starts to work normally.
5. It is better to adjust the packing
gland to make the water drop. When the vacuum pump is working under the extreme
vacuum, the explosion sound will occur due to the physical effect in the pump,
but the power consumption will not increase. If the explosion sound is found
with the increase of power, it means that the pump has failed. At this time, the
pump should be stopped immediately for inspection.
The above is about
the introduction of 2be water ring vacuum pump, and incorrect operation sequence
may lead to equipment damage. Therefore, before using the 2be water ring vacuum
pump, the user must read the operation manual carefully, understand the
operation steps and start the equipment to ensure the stability of the
equipment.