2020年4月10日星期五

2SK water ring vacuum pump installation

Before using SK vacuum pump, it is necessary to install it. At the same time, it is also necessary to install its air port. For the five steps of installing SK vacuum pump air port, simply understand:

1. In order to prevent welding slag from entering SK vacuum pump during installation, filter screen shall be installed on the suction pipe during installation;

2. The steam water separation circulating tank is a device for supplying water and circulating water to sk vacuum pump. There is a copper nozzle on the side of the tank body, which is connected with external water supply;

3. In front of SK vacuum pump, the upper part is the overflow port. When the liquid level in the tank is higher than a certain position, the water is discharged here. At the bottom of the cylinder is the drain valve, which is used to discharge the dirt;

4. The best use of the steam water separation circulating tank is: after the water is introduced from the side, it flows out from the overflow port. At this time, turn down the flow, let the water circulate and discharge all the time, take away the heat generated by the work, which is conducive to its vacuum degree and service life;

5. After SK vacuum pump is installed at the air port, the working fluid pipeline shall be installed, and the working fluid required in production shall be firmly connected with the working fluid supplement port.

I believe that you have already understood the installation steps of SK vacuum pump in the air port. I hope that the above knowledge will bring benefits to you and help you at the same time.

Vacuum Pump System Performance Parameters

Portable Vacuum Pump

Water Ring Pump

没有评论:

发表评论